| 2021 STREET CONSTRUCTION UPDATES |
| AUGUST 9 – AUGUST 13 | AUGUST 16 – AUGUST 20 |
Winneconne Av
(Commercial - Washington)
Washington Av
(Commercial - Winneconne)
Olive St | The contractor is scheduled to complete storm sewer construction and continue water main construction. The contractor will start house-side sewer and water service replacement.
All Streets, including Winneconne Avenue, will be closed to through traffic. | The contractor is scheduled to continue house-side sewer and water service replacement. |
Fairview Av | The contractor is scheduled to finish grading the roadway and place string-line in preparation for paving the south half of the street.
Driveway access to homes on the south side of the street will be restricted from the point that the string-line is placed until the concrete has cured. | The contractor is scheduled to pave the south half of the street.
Driveway access to homes on the south side of the street will be restricted from the point that the string-line is placed until the concrete has cured. |
Laudan Blvd
(Congress - S. Park) | The contractor is scheduled to do several small utility structure repairs. | No work is scheduled. |
Marathon Av
(Bell - Peckham) | The contractor is scheduled to place string-line in preparation for paving the east half of the street.
Driveway access to homes on the east side of the street will be restricted from the point that the string-line is placed until the concrete has cured. Pavement gaps will be provided at intersections. | The contractor is scheduled to pave the east half of the street.
Driveway access to homes on the east side of the street will be restricted from the point that the string-line is placed until the concrete has cured. Pavement gaps will be provided at intersections. |
Isabella St
(Winneconne-Sherry) | The contractor is scheduled to start house-side sewer and water service replacement. | The contractor is scheduled to continue house-side sewer and water service replacement. |