| WEEK OF
JUNE 21 – JUNE 25 | WEEK OF
JUNE 28 – JULY 2 |
Winneconne Ave.
(Commercial - Washington)
Washington Ave.
(Commercial - Winneconne)
Olive Street | No activities scheduled | The contractor is scheduled to mobilize equipment in preparation of beginning construction July 5. |
Fairview Avenue | The project is in a rest period. | The project is in a rest period. |
Laudan Boulevard
(Congress to S. Park) | WE Energies is scheduled to continue gas main and service replacement. | WE Energies is scheduled to continue gas main and service replacement. |
Marathon Avenue
(Bell to Peckham) | The contractor is scheduled to finish private sewer and water service construction. | WE Energies is scheduled to continue gas main and service replacement. |
Isabella Street
(Winneconne-Sherry) | The contractor is scheduled to finish sanitary sewer main construction. | The contractor is scheduled to continue water main construction. |