2021 STREET CONSTRUCTION UPDATES


“Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.”

WEEK OF
JUNE 1 – JUNE 4
WEEK OF
JUNE 7 – JUNE 11
Fairview AvenueWE Energies is scheduled to continue gas main and service replacement. WE Energies is scheduled to finish gas main and service replacement.
Laudan Boulevard
(Congress to S. Park)
The contractor is scheduled to finish private sewer and water service construction. WE Energies is scheduled to begin gas main and service replacement.
Marathon Avenue
(Bell to Peckham)
The contractor is scheduled to finish water main and storm lateral construction. The contractor is scheduled to install water waste force main. WE Energies is scheduled to continue gas main and service replacement.
Isabella Street
(Winneconne-Sherry)
The contractor is scheduled to begin sewer main construction. The contractor is scheduled to continue sewer main construction.

Notes: 1) This schedule could vary depending on site conditions and weather.

2) Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.

3) Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.

4) Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.