| WEEK OF
JULY 6 – JULY 9 | WEEK OF
JULY 12 – JULY 16 |
Winneconne Ave.
(Commercial - Washington)
Washington Ave.
(Commercial - Winneconne)
Olive Street | The contractor is scheduled to begin sewer construction. All Street including Winneconne Avenue will be closed to through traffic. | The contractor is scheduled to continue sewer construction. |
Fairview Avenue | The project is in a rest period. | The project is in a rest period. |
Laudan Boulevard
(Congress to S. Park) | WE Energies is scheduled to continue gas main and service replacement. | WE Energies is scheduled to continue gas main and service replacement. |
Marathon Avenue
(Bell to Peckham) | WE Energies is scheduled to continue gas main and service replacement. | WE Energies is scheduled to continue gas main and service replacement. |
Isabella Street
(Winneconne-Sherry) | The contractor is scheduled to finish sanitary sewer main construction and continue water main construction. | The contractor is scheduled to continue water main construction. |