| 2021 STREET CONSTRUCTION UPDATES |
| AUGUST 30 – SEPTEMBER 3 | SEPTEMBER 6 – SEPTEMBER 10 |
Winneconne Av
(Commercial - Washington)
Washington Av
(Commercial - Winneconne)
Olive St | The contractor is scheduled to finish house-side sewer and water service replacement.
All Streets, including Winneconne Avenue, will be closed to through traffic. | |
Fairview Av | The contractor is scheduled to finish concrete pavement construction. | The contractor is scheduled to begin concrete driveway and sidewalk construction. |
Laudan Blvd
(Congress - S. Park) | The contractor is scheduled to begin concrete curb and gutter and sidewalk repairs. | The contractor is scheduled to begin concrete driveway and sidewalk repairs. |
Marathon Av
(Bell - Peckham) | The contractor is scheduled to set string-line and adjust gravel on the west half of the street.
Driveway access to homes on the west side of the street will be restricted from the point that the string-line is placed until the concrete has cured. Pavement gaps will be provided at intersections. | The contractor is scheduled to pave the West half of the road.
Traffic will be restricted to Northbound traffic on Marathon Avenue until concrete street construction is completed.
|
Isabella St
(Winneconne-Sherry) | The contractor is scheduled to finish house-side sewer and water service replacement. | |